What is the appropriate value to populate in TransmissionChargeIdentification field?
Schedule5 defines which party pays the transmission charges.
It is a schedule to the GTMA (UK electricity trading master agreement).
The requirements are either Schedule 5 on or Schedule 5 off
By default this is set to ‘Off’.
Related Articles
Is Total Contract Value a matching field?
On 16 June 2014 Equias asked the eCM community for feedback regarding issues in matching the 'Total Contract Value' field. It was decided by democratic vote that it will be removed from the matching criteria and set to an information ONLY field The ...
What value should you use for the field "Contract Capacity"?
The EFET eCM Standard states that the 'Contract capacity' field is Mandatory for all trades submitted with section TIME INTERVAL QUANTITIES (1-N). The 'Contract Capacity' is "the contract capacity of the commodity that has been negotiated". The field ...
How do we populate field 'EnergyAccountType' for GB Power Trades submitted to CMS?
The eCM Standard suggests that field 'EnergyAccountType' is a mandatory field for all GB Power trades, and can be determined using 'Definitions within the Balancing & Settlement Code for the UK electricity market'. Field 'EnergyAccountType' should be ...
FixedOrFloating aggregation key field
For FixedOrFloating aggregation key field to be ‘Fixed’ all elements of the trade need to be fixed. This can be categorized as below: • TransactionTypoe = “FOR” then use “Fixed” • TransactionTypoe = “PHYS_INX” then use “Float” • TransactionTypoe = ...
Help us to define what value we could input in the field TradeConfirmation/CapacityUnit
In summary MWh/h = MW, so the CpML UoM for MWhperHour is simply MW. For the CapacityUnit should be “MW” if the rate is hourly for an hourly energy volume. For daily rate for an hourly volume the UoM “MWhperDay” should be used. If you use “MW” in your ...